Chandan Nagar RUB to become reality today : The Tribune India

Join Whatsapp Channel

Chandan Nagar RUB to become reality today

JALANDHAR: Having been proposed by the Municipal Corporation (MC) since August 2010 and remaining mired in various controversies pertaining to land acquisition for nearly five and a half years, the much-awaited Chandan Nagar Railway Under Bridge (RUB) will be finally opened tomorrow afternoon.

Chandan Nagar RUB to become reality today

The Chandan Nagar RUB which will be inaugurated in Jalandhar on Wednesday



Deepkamal Kaur

Tribune News Service

Jalandhar, September 27

Having been proposed by the Municipal Corporation (MC) since August 2010 and remaining mired in various controversies pertaining to land acquisition for nearly five and a half years, the much-awaited Chandan Nagar Railway Under Bridge (RUB) will be finally opened tomorrow afternoon.

Chief Minister Parkash Singh Badal is slated to attend the inauguration function. Hoardings were put up across the entire city today by Jalandhar (North) MLA KD Bhandari taking credit for getting his election promise fulfilled well in time. Bhandari had, twice in the 2007 and 2012, made this underbridge his poll agenda like former minister and his Congress rival Avtar Singh Henry.

However, the delay and change in plans cost the MC dear. The project for which Rs 8 crore estimates were made in August 2010 was later proposed to be of Rs 21 crore and then Rs 41 crore at the time of Bhoomi Pujan two years ago. As it has got accomplished now, Mayor Sunil Jyoti today said that the overall cost had come to Rs 45 crore now.

The MC had got the work done through the PWD. The total construction time of the bridge had been fixed as 14 months initially by which the work was to be done by the end of October 2015.

The bridge has a height of just 3 metres and will be used only for the passing of light transportation vehicles. The construction of ramps, streetlights, maintenance and pumping out of rainwater has been done by the Jalandhar MC. Residents of nearly 50 colonies, including Sodal Area, Industrial Area, Preet Nagar, Dada Colony, Globe Colony and Shiv Nagar which fall on the other side of the railway crossing, will be benefited with the opening of the bridge. Their passage gets closed as many as 120 times a day owing to the frequent passage of trains between Jalandhar and Amritsar.

Students of Shiv Joti Public School, Seth Hukum Chand School and SD School, which fall on either side of the track, were also much affected. Quite a few accidents have taken place at the crossing in the recent past, especially around Sodal Mela during which there is much rush across the crossing site.

TIMELINE 

August 2010: MC plans construction of Chandan Nagar RUB, makes an estimate of Rs 8 cr

January 5, 2011: A resolution regarding its construction passed in the MC House

January 19, 2011: Local Bodies Department approves the resolution

September 27, 2011: Land Acquisition Collector asks MC Commissioner to deposit an amount of Rs 16.38 lakh for acquisition. No funds transferred owing to paucity

April 9, 2012: PWD asks MC to deposit an amount of Rs 8.64 lakh with the Railways for the span portion

August 23, 2013: Land acquisition notification lapses, making the local BJP leaders tizzy. Bhandari rushes to Chandigarh to get it revoked and seek grants for the project

November 18, 2013: District Land Price Fixation Committee headed by DC finalises Rs 5.1 lakh a marla compensation for the acquisition of the 10 kanal 19 marla land. The land included two godowns and the playground of SD Devi Sahai School. LAC seeks an amount of Rs 16.76 crore from MC Commissioner

November 19, 2013: SE of B& R seeks the amount from Secretary Local Bodies and GM PMIDC

December 4, 2013: Objections raised by land owners. The acquisition amount raised to Rs 18.12 crore. MC arranges for the extra amount from its side

December 16, 2013: Compensation of Rs 18.12 crore released to land owners for acquisition 

August 26, 2014: Bhoomi Pujan and start of construction 

October 2015: Deadline initially fixed for completion of project

September 28, 2016: Formal opening to be held

Top News

Lok Sabha elections 2024: PMK gets 10 seats in seat-sharing deal with BJP in Tamil Nadu

Lok Sabha elections 2024: PMK gets 10 seats in seat-sharing deal with BJP in Tamil Nadu

The PMK is a Vanniyar community-dominated party and has sign...

H-1B initial registration period to close on March 22

H-1B initial registration period to close on March 22

Online account users will also be able to collaborate on reg...

INDIA VOTES  2024: Election Commission orders removal of Bengal DGP, home secys of 6 states

INDIA VOTES 2024: Election Commission orders removal of Bengal DGP, home secys of 6 states

TMC terms directive glaring example of BJP’s ‘control’ over ...

PM Modi tears into Rahul over ‘fighting against shakti’ remark

PM Modi tears into Rahul over ‘fighting against shakti’ remark

Didn’t mean it in religious terms, talked about corruption: ...


Cities

View All