CHANDIGARH: The solution to silt accumulation in Harike lake — the largest wetland in North India — is finally in sight with the help of pontoon gates.

Pontoon gates to rid Harike wetland of silt

The rusted gates of the Harike headworks that are set to be replaced. Tribune photo



Varinder Singh

Tribune News Service

Chandigarh, July 11

The solution to silt accumulation in Harike lake — the largest wetland in North India — is finally in sight with the help of pontoon gates.

The multi-gated Harike headworks were constructed in 1953 and was located downstream of the confluence of the Sutlej and Beas rivers.

The 4,100 hectare wetland displaying a rich biodiversity had got endangered due to accumulating silt. The depth of the lake had come down from 23 feet to a mere 10-11 feet.

The flow of the Sutlej and the Beas river waters was controlled at the headworks by 48 steel gates. These gates were set up to control the flow of water and make it available to Rajasthan and parts of Southern Punjab. Excess water was going to Pakistan via the Sutlej.

Silting had taken place in the Harike lake and its catchment area over the years as 31 gates meant for flow of excessive water downstream were rusted and useless.

Flooding of the catchment area of Sutlej and Beas had almost become an annual feature in monsoons for these 31 gates meant for release of excessive water in Sutlej were hardly opened during the past 63 years.

The Irrigation Department was on a lookout for a technology which could enable it to get the gates repaired after installing alternative gates.

“Our biggest problem was that unlike other headworks, the Harike headworks were sans any grooves where alternative steel gates could be inserted temporarily,” said an official.

Rust had damaged the old gates that these could not be removed for over six decades. Moreover, the replacement of gates without making alternative arrangements could have played havoc with lives of people along Sutlej,” said KS Pannu, Principal Secretary, Irrigation.

A Vishakhapatnam- based company specialising in pontoon bridge technology has come to the rescue of the problem. Now, pontoon gates would be installed during the replacement of the rusted gates.

“The replacement would cost around Rs. 14 crore and the exercise would be completed by September,” said Pannu.

“The water hycinth would be removed by a new machine being imported for Rs 2.5 crore, he added.

The department was also trying to control the growth of water haycinth with the help of weedicides.

Top News

Chief Judicial Magistrate's court in UP's Banda orders judicial inquiry into death of gangster-politician Mukhtar Ansari

Judicial inquiry ordered into death of gangster-politician Mukhtar Ansari

Asks additional CJM to conduct probe into Mukhtar Ansari's d...

Cash-strapped Congress gets fresh IT notice of Rs 1,700 crore, say party insiders

Cash-strapped Congress gets fresh I-T notice of Rs 1,800 crore

Ajay Maken addresses a press conference

Special court convicts 7 people in BSP MLA Raju Pal murder case

Special court convicts 7 people in BSP MLA Raju Pal murder case

The proceedings against Atiq Ahmad, his brother and prime ac...

Arvind Kejriwal's wife releases WhatsApp number for people to send messages for jailed AAP leader

Arvind Kejriwal's wife launches WhatsApp campaign to garner support for AAP leader

In a digital media briefing, Sunita says her husband has cha...


Cities

View All