Slow-paced work on Rohtang tunnel worries state : The Tribune India

Join Whatsapp Channel

Slow-paced work on Rohtang tunnel worries state

SHIMLA: Fearing further delay in the completion of the Rohtang tunnel, the state government has urged the Centre to expedite the installation of a quarry plant at the north portal of the tunnel so that the project can be completed by 2019.

Slow-paced work on Rohtang tunnel worries state

The pace of work has slowed down considerably as the Union Ministry of Environment and Forest has delayed the permission to install the high-tech machine which will help throw out the excavated muck from inside the tunnel.



Pratibha Chauhan

Tribune News Service

Shimla, June 29

Fearing further delay in the completion of the Rohtang tunnel, the state government has urged the Centre to expedite the installation of a quarry plant at the north portal of the tunnel so that the project can be completed by 2019.

The pace of work has slowed down considerably as the Union Ministry of Environment and Forest has delayed the permission to install the high-tech machine which will help throw out the excavated muck from inside the tunnel. The concreting of the tunnel can begin only after completing this task.

Chief Secretary VC Pharka has taken up the matter with the Union Ministry of Forest and Environment. “I have spoken to the Director General of the Ministry of Environment and Forest, SS Negi, requesting him to get the clearance expedited as this was delaying the completion of the Rohtang tunnel,” said Pharka. He added that the Principal Chief Conservator, Forests, (PCCF) had been asked to pursue the grant of an NOC with the Centre.

Ravi Thakur, legislator from the tribal district of Lahaul and Spiti, whose constituents stand to benefit from the completion of the tunnel has also taken up the matter with the Union Forest Secretary and other central agencies. “The panchayats of Koksar and Palchang have already been given the NOC and the Ministry of Environment and Forest is delaying the project,” said Ravi.

He lamented that despite the fact that there were hardly any trees or green cover in the area, the ministry was dilly-dallying in giving the NOC. He said the completion of the tunnel would benefit the people of Lahaul-Spiti and as such there should be no further delay.

The government is worried that in case of delay, the project could be pushed further, thereby leading to even substantial cost escalation.

The foundation stone of the project was laid in 2009 and the work had started two years later. The cost which was initially pegged at Rs 1,355 crore has now shot up to Rs 2,200 crore.

Project cost escalates

  • The pace of work has slowed down considerably as the Union Ministry of Environment and Forest has delayed the permission to install the high-tech machine which will help throw out the excavated muck from inside the tunnel
  • Chief Secretary VC Pharka has taken up the matter with the Union Ministry of Forest and Environment
  • The foundation stone of the project was laid in 2009
  • The cost which was initially pegged at Rs 1,355 crore has now shot up to Rs 2,200 crore

Top News

Israel says it is poised to move on Rafah

Israel says it is poised to move on Rafah to assault Hamas hold-outs

Netanyahu's Government said Israel 'moving ahead' with groun...

Tibetan government-in-exile, China holding back-channel talks; aiming to revive stalled dialogue process

Tibetan government-in-exile, China holding back-channel talks; aiming to revive stalled dialogue process

From 2002 to 2010, Dalai Lama’s representatives and Chinese ...

JEE-Main 2024 result declared; 56 candidates score 100 percentile

JEE-Main 2024 result declared; 56 candidates score 100 percentile

Out of 56, 15 are from Telangana, 7 each from Andhra Pradesh...

DRG cop killed, another injured in accidental firing in Chhattisgarh’s Dantewada

DRG cop killed, another injured in accidental firing in Chhattisgarh’s Dantewada

The incident took place around 11 pm on Wednesday, say polic...

Phase-2 campaign ends, fate of Rahul, Shekhawat, HDK, Hema to be sealed

Phase-2 campaign ends, fate of Rahul Gandhi, Gajendra Shekhawat, HD Kumaraswamy, Hema Malini to be sealed

88 seats up for grabs across 13 states | Polling to conclude...


Cities

View All