Satya Niketan collapse lands before Delhi HC through 2 legal moves
7 persons were killed after the multi-storey building, being used as a PG near Delhi University’s South Campus, collapsed on Sunday
A day after seven persons were killed in the collapse of a multi-storey paying guest accommodation in Satya Niketan, the tragedy landed before the Delhi High Court through two legal moves on Monday — a fresh PIL seeking Rs 1 crore compensation for the victims’ families and a structural audit of PGs across the Capital, and an application seeking urgent hearing of an already pending case on Delhi’s crumbling administrative and physical infrastructure.
The fresh PIL, filed by Aniket Kumar Gupta, was mentioned for urgent hearing before a Bench of Chief Justice D K Upadhyay and Justice Tejas Karia, which agreed to hear the matter.
Also read: Delhi building collapse: Owner Hariram Gupta arrested from Rajasthan’s Bhiwadi
Delhi building collapse: Death toll climbs to 7, 12 rescued from debris in Satya Niketan
MCD orders demolition of Satya Niketan building after fatal collapse
Delhi PG hostel collapse: CCTV captures moment Satya Niketan structure crashes into rubble
Separately, an application moved through advocate Rudra Vikram Singh sought preponement of the hearing in the pending writ petition from November 6, arguing that the September 6 Satya Niketan building collapse and the loss of lives had brought renewed urgency to questions over unauthorised construction, structural safety and enforcement of building norms in Delhi.
The application assumes significance as the High Court had as far back as August 2024 held that Delhi’s administrative, physical and financial infrastructure “needs a re-look” by an expert body and ordered the constitution of a high-level committee comprising some of the Capital’s top officials.
The fresh PIL, meanwhile, has sought an independent and comprehensive investigation into the collapse, including scrutiny of the role of the owners, builders, contractors, architects, structural engineers, those involved in renovation work and public authorities responsible for enforcing building regulations.
At least seven persons were killed after the multi-storey building, being used as a PG near Delhi University’s South Campus, collapsed on Sunday. An FIR has been registered against the person running the accommodation, who was nabbed on Monday from Bhiwadi in Rajasthan.
According to the PIL, preliminary reports indicated that repair, renovation or construction-related work was allegedly being undertaken immediately before the building collapsed.
The plea said the tragedy had thrown up questions over the legality of such work, the building’s structural integrity, compliance with sanctioned plans, permission for its use as a PG or hostel, structural stability certification, fire safety compliance and the adequacy of inspections by statutory authorities.
Apart from Rs 1 crore compensation for the families of the victims, Gupta has sought an immediate comprehensive structural safety audit of PGs, hostels and student accommodation premises in Satya Niketan as well as other major student accommodation clusters across Delhi.
In the parallel legal move, the Satya Niketan tragedy has been placed before the High Court as a subsequent development in an older petition concerning the functioning of authorities responsible for Delhi’s administration, planning, development, maintenance and regulation.
The application said the collapse had once again brought to the forefront the larger problem of unauthorised and unsafe construction and the need for effective inspections, identification of unsafe structures, enforcement of building regulations and coordination among different authorities.
The pending petition carries a significant judicial history. On August 2, 2024, the High Court had observed that Delhi’s administrative, physical and financial infrastructure “needs a re-look” by an expert body.
The court was initially inclined to constitute a committee headed by the Union Home Secretary. However, at the request of the Delhi Government’s standing counsel, it instead constituted a committee headed by the Chief Secretary and comprising the MCD Commissioner, DDA Vice-Chairman, Delhi Police Commissioner and NDMC Chairman.
The committee was directed to submit a report containing its suggestions within eight weeks. But when the report came up for consideration on November 28, 2024, the High Court found that it was confined to Delhi’s drainage system and did not cover the entire mandate concerning the Capital’s administrative, physical and financial infrastructure.
It then directed the committee to place a detailed report containing “concrete” recommendations on all three aspects before the court.
The early-hearing application has now argued that the larger issues continue to remain pending despite those directions and that Sunday’s fatal collapse demonstrates why they require urgent judicial consideration.
It said concerns over unauthorised construction, structural safety, enforcement of building norms and coordination among authorities “cannot be considered in isolation”, as they are directly linked to how Delhi’s administrative and physical infrastructure is regulated and maintained.
The main case is presently listed for November 6. The application has sought an earlier hearing, saying the latest deaths, coupled with the continued pendency of the issues previously flagged by the High Court, warrant urgent consideration.
It has also argued that an early hearing would allow the authorities to tell the court what steps they have taken and what measures they propose to prevent such incidents.