Nine national highway projects worth over Rs 12,000 cr behind schedule in Haryana
Centre cites farmer protests, excess rain, ban on felling as reasons for delays
Nine national highway (NH) projects involving the construction of 310 km of roads are running behind schedule in Haryana. Information shared in Parliament today shows that under the Bharatmala Pariyojana, NH projects covering a length of about 1,114 km, with a sanctioned cost of Rs 50,187 crore, were sanctioned and awarded in Haryana.
Of these, 27 projects covering a length of about 804 km have been completed and the balance nine projects are under various stages of implementation. The project pendency rate in the state is 28%.
“The primary reasons for delay in NH projects are issues and bottlenecks relating to land acquisition, delay in getting statutory clearances, utility shifting, farmer protests, Graded Response Action Plan (GRAP) restrictions, nonavailability of construction material and minerals, poor performance of contractor and Concessionaire, and Force Majeure events like the Covid-19 pandemic, international wars and heavy rainfall,” Union Minister of Road Transport and Highways Nitin Gadkari said. The combined sanctioned cost of these nine projects is over Rs 12,793 crore.
The costliest among the nine pending projects is the construction of Greenfield connectivity to Jewar International Airport from the DND-Faridabad-Ballabhgarh Bypass KMP Link and Spur to the Delhi-Mumbai Expressway. This 22.3-km project, with a sanctioned cost of Rs 2,414 crore, was to be completed by June 21, 2025, but now the timelines have been delayed to April 16, 2027.
Gadkari has said the project has been delayed due to the state government’s demand to expand the elevated stretch from the currently approved 1.5 km to 9.6 km.
Likewise, the second costliest project among those that have been delayed — Rs 1,867 crore Gurgaon-Pataudi-Rewari involving the construction of 46.11 km of road on NH-352 — stands delayed by three years. Its scheduled date of completion was November 23, 2023, and it is expected to be operational by the end of September 2026. Gadkari attributed the delay to ban on tree cutting by the National Green Tribunal, demand of underpass by villagers, nonavailability of land by GMDA and delay in approval of the launching scheme by the Railways.
In most other projects that have been delayed, farmer protests, excess rainfall and ban on mining have been mentioned as the main reasons. Some other delayed projects are: 38.9 km Shamli-Ambala (Part -2) (NH-344), with a sanctioned cost of Rs 1,554.21 crore; 37.38 km Shamli-Ambala (Part-3) on NH-344, with a sanctioned cost of Rs 1,491 crore; 34.5 km Karnal Ring Road on NH-44; and 42.5 km of Ismailabad-Ambala section of NH-152.