Nerchowk-Pandoh road to remain closed for 2 hours twice near 4 Mile

In view of ongoing construction work on the Nerchowk-Pandoh four-lane highway, the road stretch near 4 Mile in Mandi district will remain closed for two hours twice every day from May 2 to 31, said Apoorv Devgan, Deputy Commissioner-cum-Chairman of...
A JCB machine removes debris on the road at 4 mile in Mandi.
Advertisement
In view of ongoing construction work on the Nerchowk-Pandoh four-lane highway, the road stretch near 4 Mile in Mandi district will remain closed for two hours twice every day from May 2 to 31, said Apoorv Devgan, Deputy Commissioner-cum-Chairman of the District Disaster Management Authority, in an order issued here.

According to the order, the highway will remain closed between 12.30 am and 2.30 am for debris removal and from 5 am to 7 am for hill-cutting work. The decision has been taken keeping in mind the urgency of the construction work, safety protocols required and the safety of commuters using the highway.

Advertisement

The Deputy Commissioner said that the road closure was necessary to ensure that the ongoing work could progress unhindered. The construction work involved the use of heavy machinery, blasting and large-scale excavation, which pose potential hazards to vehicular movement during active hours, he added.

He said, “Citizens have been urged to cooperate with the administration and plan their travel accordingly. Commuters have been advised to use alternative routes when the road is closed to avoid inconvenience.”

Devgan said that efforts were being made to minimise traffic disruption and complete the work within the stipulated time. Public cooperation, he emphasised, was crucial to ensure both progress and safety during the construction of this vital infrastructure work.