TrendingVideosIndia
Opinions | CommentEditorialsThe MiddleLetters to the EditorReflections
UPSC | Exam ScheduleExam Mentor
State | Himachal PradeshPunjabJammu & KashmirHaryanaChhattisgarhMadhya PradeshRajasthanUttarakhandUttar Pradesh
City | ChandigarhAmritsarJalandharLudhianaDelhiPatialaBathindaShaharnama
World | ChinaUnited StatesPakistan
Diaspora
Features | The Tribune ScienceTime CapsuleSpectrumIn-DepthTravelFood
Business | My MoneyAutoZone
News Columns | Straight DriveCanada CallingLondon LetterKashmir AngleJammu JournalInside the CapitalHimachal CallingHill View
Don't Miss
Advertisement

Shimla: New-look Ridge by June-end

Unlock Exclusive Insights with The Tribune Premium

Take your experience further with Premium access. Thought-provoking Opinions, Expert Analysis, In-depth Insights and other Member Only Benefits
Yearly Premium ₹999 ₹349/Year
Yearly Premium $49 $24.99/Year
Advertisement

Navneet Rathore

Advertisement

Advertisement

Shimla, April 15

The Public Works Department (PWD) will complete the work to restore the sinking part of the historic Ridge here by June-end.

The restoration work, costing Rs 67 crore, was started in 2022 under the Shimla Smart City Mission.

Advertisement

Under the project, a 70-metre long and 10-metre wide structure was to be raised to save the sinking part of the Ridge that had developed cracks several years ago. Due to this, the area opposite the Gaiety Theatre had started to sink.

The PWD has so far installed three slabs, while the last one is being inserted and the work will be completed by June-end.

With the availability of extra space after the structure is complete, the Shimla Municipal Corporation will set up benches for people.

PWD Executive Engineer Praveen K. Verma said 90 per cent of the restoration work was complete.

He said only beautification work of the terrace was remaining which would be completed by June.

To check the sinking of the Ridge, the MC, in 2019, had asked engineering experts from the Indian Institute of Technology, Roorkee, to come up with a solution.

After conducting a geotechnical study of the sinking portion, the IIT team had submitted the report to the PWD.