BRO restores connectivity on critical Mahanpur-Theyn axis in Kathua
Unlock Exclusive Insights with The Tribune Premium
Take your experience further with Premium access. Thought-provoking Opinions, Expert Analysis, In-depth Insights and other Member Only BenefitsThe Border Roads Organisation (BRO) has restored access to remote village in Kathua district where connectivity for heavy vehicles was snapped due to a major cloudburst on August 17.
“Following the devastating cloudburst incident on August 17 in the Kathua district, a major disruption occurred on the Pedu Nala along the Mahanpur–Theyn axis, resulting in the washing away of an existing bridge and an under-construction bridge,” a Defence spokesperson said.
He said this unprecedented event was caused by heavy landslides and landslips triggered by incessant rainfall, completely blocking the vital route between Ranjit Sagar Dam and Mahanpur for all types of traffic.
The aftermath presented formidable challenges, including massive debris accumulation, damaged bridge components strewn across the site, ongoing inclement weather, and the isolation of the location due to simultaneous blockages on alternate access roads.
Despite these severe conditions, 69 Road Construction Company (RCC) of Project Sampark (BRO), under the command of SK Singh, Commander of the 35 Border Roads Task Force (BRTF) based in Udhampur, launched a deliberate, methodical, and high-intensity restoration operation.
The Project Sampark team, led on-site by Assistant Engineer Surendran, worked round-the-clock to clear access to the site by mobilising excavators and heavy machinery, remove landslide debris, channelise the diverted water flow, construct box culverts, install humepipes, and build gabion walls to stabilise the area and restore the roadway.
“Their tireless efforts culminated in the restoration of the breached road section for heavy vehicular traffic by the evening of September 13, successfully re-establishing connectivity between Bilawar, Kathua, and Dhar—a vital route for local civilians and administration alike,” the spokesperson said.
Chief Engineer, Project Sampark expressed his heartfelt appreciation and commendation for the dedication and resilience demonstrated by Team 69 RCC, especially under such adverse weather and geographical conditions.