Add Tribune As Your Trusted Source
TrendingVideosIndia
Opinions | CommentEditorialsThe MiddleLetters to the EditorReflections
UPSC | Exam ScheduleExam Mentor
State | Himachal PradeshPunjabJammu & KashmirHaryanaChhattisgarhMadhya PradeshRajasthanUttarakhandUttar Pradesh
City | ChandigarhAmritsarJalandharLudhianaDelhiPatialaBathindaShaharnama
World | ChinaUnited StatesPakistan
Diaspora
Features | The Tribune ScienceTime CapsuleSpectrumIn-DepthTravelFood
Business | My Money
News Columns | Straight DriveCanada CallingLondon LetterKashmir AngleJammu JournalInside the CapitalHimachal CallingHill ViewBenchmark
Don't Miss
Advertisement

J-K’s longest flyover ready, waits for inauguration

Unlock Exclusive Insights with The Tribune Premium

Take your experience further with Premium access. Thought-provoking Opinions, Expert Analysis, In-depth Insights and other Member Only Benefits
Yearly Premium ₹999 ₹349/Year
Yearly Premium $49 $24.99/Year
Advertisement

Jammu, October 30

Advertisement

The construction of the longest flyover in Jammu and Kashmir has been completed and is awaiting a formal inauguration.

Advertisement

This 4.6 km-long flyover is built on the Jammu-Akhnoor road and connects Kanal Head to Ganesh Vihar Mithi near the Directorate of School Education, Jammu. Although it is complete, it has not been officially dedicated to the people.

The construction agency is waiting for a dignitary from the Centre to formally inaugurate it.

A company named Infrastructure Development Corporation Limited under the Union Ministry of Roads and Highways is working on the road-widening project which has a total cost of Rs 1,345 crore and has been divided into four packages.

Advertisement

The flyover has been constructed under Package II, while under Package III, 60 per cent of the work has been completed.

General Manager of Project Monitoring Unit Jammu-Akhnoor SP Sangwan told media that the Tagnesh Vihar Mithi flyover, the longest canal head in Jammu and Kashmir, has been completed quickly and there has not been a single accident on it.

The construction work started in November 2018, which was paralysed for almost two years as people from a few villages in Palura moved the high court. The land of the flyover was transferred in January 2021. Despite shortage of manpower and material, oxygen cylinders for welding due to the covid pandemic, the company completed the work by September 15, 2022.

During this time, demolition of structures, relocation of water supply line, shifting of cabling of underground 11 and 33 kV VHT line were important works. The work was allotted to M/S Singhala Construction Company, which constructed the 4.6 km-long flyover consisting of eight lanes, including four service lanes at a cost of Rs 274 crore. IANS