TrendingVideosIndia
Opinions | CommentEditorialsThe MiddleLetters to the EditorReflections
UPSC | Exam ScheduleExam Mentor
State | Himachal PradeshPunjabJammu & KashmirHaryanaChhattisgarhMadhya PradeshRajasthanUttarakhandUttar Pradesh
City | ChandigarhAmritsarJalandharLudhianaDelhiPatialaBathindaShaharnama
World | ChinaUnited StatesPakistan
Diaspora
Features | The Tribune ScienceTime CapsuleSpectrumIn-DepthTravelFood
Business | My MoneyAutoZone
News Columns | Straight DriveCanada CallingLondon LetterKashmir AngleJammu JournalInside the CapitalHimachal CallingHill View
Don't Miss
Advertisement

Work on Beas-Qadian rail track shelved due to fund shortage

Unlock Exclusive Insights with The Tribune Premium

Take your experience further with Premium access. Thought-provoking Opinions, Expert Analysis, In-depth Insights and other Member Only Benefits
Yearly Premium ₹999 ₹349/Year
Yearly Premium $49 $24.99/Year
Advertisement

Ravi Dhaliwal

Advertisement

Tribune News Service

Advertisement

Qadian, December 13

Regular protests by farmers against acquisition of their land and paucity of funds on the part of the Punjab Government have combined to sound the death knell of the strategically important 40-km-long Qadian-Beas rail link, one of the most talked about projects of the district.

The rail linkage was vital in many respects. Beas is the headquarters of the Radha Soami sect while Qadian houses the Ahmadiyya community’s international headquarters. The venture could have placed Batala on the high speed Amritsar-Delhi line thus proving to be a boon for industrialists as far as connectivity with the national capital was concerned. It would also have facilitated the smooth movement of armed forces in the border area.

Advertisement

In 2010, the then Rail Minister Mamata Banerjee, acting on a request made by MP Partap Singh Bajwa, had sanctioned the track under the socially desirable rail connectivity proposals scheme. At that time, its cost was pegged at Rs 205.22 crore and work was envisaged to be completed by 2024. The cost has now escalated to a whopping Rs 840 crore. Half the amount was to be paid by the Punjab Government in the form of a matching grant which, in any case, is not forthcoming.

Qadian MLA Fateh Jung Singh Bajwa said at present, Qadian and Beas towns were connected by a circuitous route. He said he would take up the issue with CM Capt Amarinder Singh. The fact that the project had been shelved would not have come to light but for the efforts of Batala resident Jagjot Singh Sandhu. Sandhu had written to the Railways asking for information about the track’s progress. The answer he got was “work has been kept in abeyance”. The distance between Qadian and Beas would have been reduced to 28 km from the present 58 km.

Project cost escalated to Rs 840 crore