Another step forward towards land acquisition : The Tribune India

Join Whatsapp Channel

Another step forward towards land acquisition

LUDHIANA: Yet another step forward has been taken for acquisition of land measuring 161.27 acre at Aitiana village in Raikot tehsil of this district for setting up an international airport at Halwara.

Another step forward towards land acquisition

Process for acquisition of land for international terminal at Halwara Airport is in progress. Tribune photo



Kuldip Bhatia

Ludhiana, November 15

Yet another step forward has been taken for acquisition of land measuring 161.27 acre at Aitiana village in Raikot tehsil of this district for setting up an international airport at Halwara. The relief and rehabilitation (R&R) report for the land owner families to be affected from acquisition of land as required under Section 18 of the Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement (LARRA) Act 2013 has been approved by the Commissioner of Patiala Division in the capacity of Relief and Rehabilitation Commissioner (Patiala Division).

Granting nod to the R&R submitted by the Greater Ludhiana Area Development Authority (GLADA) vide his office letter no. MS/6226 dated October 29, the Commissioner said the approval was subject to the condition that all provisions laid down in the Act had been complied with.

The proposed international zirport at Halwara, third in the state of Punjab after Amritsar and Mohali, is to be constructed over 161.27 acre at Aitiana village and land acquisition notice was issued by the Department of Housing and Urban Development on July 17 under section 11 of LARRA Act 2013. The airport is to be jointly constructed by the Airport Authority of India and the Punjab Government (through GLADA).

The R&R report mentions that out of the total land proposed to be acquired for the project, 150 acre was privately owned and 90 families cultivating this land were likely to be affected. Ownership of the rest of the land vested with the state government.

In the report, prepared under section 16 of the Act after mandatory ‘social impact assessment’ of the project-affected families and public hearing of all stake holders, it has been proposed that a one-time resettlement allowance of Rs 50,000 would be granted to each family in addition to compensation of land at the rate of Rs 5.50 lakh per acre.

Timeline

December 3, 2018: Project gets nod from Punjab Cabinet

December 20, 2018: MOU signed between Punjab Government and AAI for the project

February 28, 2019: Notification issued under Section 4 (1) of the Act for Social Impact Assessment

May 2, 2019: Public hearing of persons likely to be affected by acquisition of land under Section 5 of the Act

July 17, 2019: Notification for acquisition of 161.27 acre land in Aitiana village issued under Section 11 of the Act

September 2019: Public hearing of land owners held

October 2019: Approval of Relief and Rehabilitation scheme from Commissioner, Patiala Division

December 2019: Data collection for transfer of compensation amount to land owners

December 2019: Disbursement of compensation and resettlement allowance to land owners