Stones laid in 2015, no work on building, bridge yet

NURPUR: A sub-tehsil building and a bridge on the local Gaj rivulet in Nagrota Surian, Jawali, foundations stones of which were laid by the then Chief Minister, Virbhadra Singh, on February 15, 2015, are yet to see the light of day.

editorial@tribune.com

Rajiv Mahajan

Nurpur, August 12

A sub-tehsil building and a bridge on the local Gaj rivulet in Nagrota Surian, Jawali, foundations stones of which were laid by the then Chief Minister, Virbhadra Singh, on February 15, 2015, are yet to see the light of day.

High-velocity winds had damaged the foundation stone, along with the plaque of the Gaj rivulet bridge, a few years ago whereas the site for the sub-tehsil building has become a dumping site and a shelter for stray cattle.

As per information, the Revenue Department had proposed the construction of the sub-tehsil building at Nagrota Surian at a cost of Rs 35 lakh, but its construction never started. The identified site is without any parking space. Sources said after the state government came to power, the project was shelved. It was decided that the existing two-room building of the sub-tehsil would be reconstructed.

The former Chief Minister had also laid the foundation stone of Gaj rivulet bridge on Nagrota Surian-Chalwara-Farian link road the same day, but its construction could not be started by the PWD.

The proposed 828-m bridge had to be constructed at an estimated cost of Rs 58 crore. After its construction, the distance between Jawali and surrounding gram panchayats Ghar-Jarot, Nagrota-Surian, Haar and Chalwara will reduce by 8 to 10 kilometres. Similarly, the distance between Jarot panchayat and Nagrota Surian will reduce to merely 2 kilometre. At present, the residents of this panchayat have to travel 10 kilometer to reach Nagrota Surian town. Raman Kumar, Sushma, Hem Chand, Om Parkash and Rakesh, residents of Jarot said in emergency the people had to cross the rivulet to reach Nagrota Surian, which was risky in monsoon. Executive Engineer, Public Works Department, Jawali division, Jagtar Singh said the construction of the proposed bridge could not be started as no funds were allocated for the project. He admitted that construction on the identified site, where the bridge had been proposed, was practically not feasible.

Cities

View All

19 cell phones, Rs 6,500 seized from Central Jail in two days

Search op being carried out daily to check use of mobiles in...

‘Cervical cancer is preventable, HPV vaccine must’

Phulkari-CAN organises 44th cervical cancer awareness sessio...

Day after, DSP's wife takes U-turn

Says no shot fired, cops concocted story

NZC fails to end Chandigarh airport name deadlock

Haryana says ready to leave claim if Punjab returns amount s...

Plea in top court over Shaheen Bagh blockade

In its verdict earlier, the Delhi HC didn't order blockade l...

MC goes slow on Rs5-cr rent dues

Few traders have not paid rent for a decade

Traders meet Police Commissioner

Accuse GST officials of filing false case; CAs also hold pro...