Himachal CM opens incomplete hospital building, triggers controversy : The Tribune India

Join Whatsapp Channel

Himachal CM opens incomplete hospital building, triggers controversy

Action demanded against officials for keeping Thakur in the dark

Himachal CM opens incomplete hospital building, triggers controversy

The Civil Hospital building, Palampur, which was recently inaugurated by the Chief Minister.



Ravinder Sood

Palampur,  April 28

The inauguration of an incomplete building of the Civil Hospital and a bridge by Chief Minister Jai Ram Thakur in Palampur recently has triggered a controversy. Action is being demanded against state officials for keeping the  Chief Minister in the dark about the building and the bridge. However, the officials concerned are tight-lipped on the issue. 

Thakur, during a visit to Palampur on April 14, had inaugurated the Civil Hospital complex built at a cost of Rs 15 crore but the building is still incomplete and it would take months to make the new complex functional. 

Incomplete bridge also inaugurated

  • The CM also inaugurated a bridge over the Lingti Khud, 10 km from Palampur
  • The approach roads to the bridge are still incomplete
  • The half-completed bridge has been opened to traffic, posing threat to commuters
  • Local MLA Ashish Butail says that the government must inquire into the matter

The district administration was either not aware or deliberately covered up the fact. The Chief Minister has inaugurated the building but the Health Department is yet to take its possession. It has asked the PWD to hand over a fully operational building. 

BM Thakur, Executive Engineer, PWD, admits that he had issued the completion certificate only pertaining to civil works. The other installations such as elevators, power connection and fire-fighting equipment are beyond his purview.   

Information gathered by The Tribune reveals that the building is yet to get the power connection from HP State Electricity Board Limited. 

Executive Engineer, HPSEBL, Sandeep Kumar says that he  has submitted an estimate of Rs 30 lakh  to the Health Department for the installation of transformers in the complex.  However, no funds have been released. 

Likewise, the installation of elevators and firefighting equipment is also pending because of some technical issues and the want of funds.  MC Patial, Executive Engineer, PWD (Electrical), says that the matter is under process. 

The Chief Minister also inaugurated a bridge over the Lingti Khud, 10 km from Palampur. The approach roads to the bridge are still incomplete.  The half-completed bridge has been opened to traffic, posing a threat to the lives of commuters. 

Local MLA Ashish Butail says that the government must inquire about who misguided the Chief Minister to  inaugurate the half-completed building and the bridge.  He adds as the Assembly elections are due in November, BJP leaders are inaugurating the half-completed project in a hurry. 


Top News

Supreme Court to deliver verdict on PILs seeking 100 per cent cross-verification of EVM votes with VVPAT today

Supreme Court dismisses all petitions seeking 100% cross-verification of EVM votes with VVPAT

A Bench of Justice Sanjiv Khanna and Justice Dipankar Datta ...

Nirmala Sitharaman, Narayana Murthy, Rahul Dravid among early voters in Bengaluru

Nirmala Sitharaman, Narayana Murthy, Rahul Dravid among early voters in Bengaluru

Many booths reported brisk voting in the first hour of polli...

London resident Inderpal Singh Gaba arrested by NIA in Indian mission attack case

London resident Inderpal Singh Gaba arrested by NIA in Indian mission attack case

On March 19, a large group of protesters were found to have ...

Selja picked for Sirsa, Deepender Rohtak

In Haryana, Kumari Selja picked for Sirsa Lok Sabha seat, Deepender Hooda Rohtak

Congress’s Haryana list of 8 out | Birender’s son denied His...


Cities

View All