Sawra Kuddu project to start power generation by April : The Tribune India

Join Whatsapp Channel

Sawra Kuddu project to start power generation by April

Sawra Kuddu project to start power generation by April

The first unit of 111 MW Sawra Kuddu Hydroelectric Project will start generating power by April. Process of filling head race tunnel of project will start shortly. Tribune photo



S & agency

Shimla, February 21

After running seven years behind schedule, the first unit of 111 MW Sawra Kuddu Hydroelectric Project in Shimla district will start generating power by April, Himachal Pradesh Power Corporation Ltd (HPPCL) said on Thursday.

It will be the most expensive project to date in Himachal as one megawatt will cost Rs 14.41 crore. The cost of per megawatt in other projects is pegged at Rs 10 crore.

The cost of the project has been revised to Rs 1,600 crore, director, civil, HPCL, DS Thakur said. The project would generate 386 million units that would earn a revenue of Rs115 crore per annum, he added.

As per the detailed project report of 2005, the project was estimated to cost Rs 558 crore. But the tender was delayed by two years, Thakur said.

The HPCL attributed the cost overrun to increase in land award, delays due to unexplained geological surprises and in the construction of head race tunnel. Tunnel contractor was changed that delayed the work by two years, Thakur claimed.

The HPCL had failed to address the grievances of villagers of Thana. They had moved the National Green Tribunal seeking relief for drying up water sources and cracks in houses, said Govind Chatranta, a villager.

The process of filling headrace tunnel will start shortly, Thakur said. He said the execution of the project started in June 2007. The main bottleneck in its construction was excavation of 11.365 km headrace tunnel owing to adverse geological rock conditions.

Besides tough rock strata, high ingress of water along with flowing rock conditions at various locations had to be tackled cautiously with high engineering proficiency.

The work of the barrage was awarded to Patel Construction Company and headrace tunnel was initially awarded to Aban Coastal joint venture in June 2007.

Later, the barrage construction was carried out by Hindustan Construction Company Ltd in November 2014.

The project comprises a diversion barrage on the Pabbar river near Hatkoti and underground powerhouse on the left bank of the river near Snail village.

After commissioning the project, each project affected family will be provided 100 units of electricity per month free for 10 years. In addition, 1 per cent of the revenue from power generation will be contributed to the local area development during the operation stage.


Top News

Indore Lok Sabha seat Congress nominee Akshay Bam withdraws candidature

Congress's Indore nominee Akshay Bam withdraws candidature; likely to join BJP

The Congress had fielded Bam (45), a newbie in the poll aren...

Tihar jail administration allows wife Sunita to meet Arvind Kejriwal

Tihar jail administration allows wife Sunita to meet Arvind Kejriwal

She was denied permission on Sunday to meet him

3 drug peddlers arrested, 48 kg heroin seized in Jalandhar

3 drug peddlers arrested, 48 kg heroin seized in Jalandhar

FIRs have been filed under the NDPS Act

NEET aspirant from Haryana hangs self in Kota; parents suspect murder, demand fair probe

NEET aspirant from Haryana hangs self in Kota; parents suspect murder

This is the seventh case of suspected suicide by a NEET or J...


Cities

View All