Work picks up pace to construct Ludhiana-Bathinda highway : The Tribune India

Join Whatsapp Channel

Work picks up pace to construct Ludhiana-Bathinda highway

Package-1 of 75.5-km Rs 2,462-crore Greenfield project to complete by 2025

Work picks up pace to construct Ludhiana-Bathinda highway

The work in progress to construct the Ludhiana-Bathinda highway in Ludhiana on Wednesday. Photo: Ashwani Dhiman



Tribune News Service

Nitin Jain

Ludhiana, March 6

The work to construct the much-awaited Ludhiana-Bathinda highway has picked up pace, the National Highways Authority of India (NHAI) has said.

Even as the physical possession of 26.5 per cent of the total land required for the 30.3-km-long Package-1 of the Greenfield project was yet to be taken over, the construction work for this component at the cost of Rs 906.51 crore has already achieved 17 per cent completion so far.

However, the acquisition proceedings for almost the entire land measuring 323.52 hectares for 45.243-km Package-2 of the highway project to be built at the cost of Rs 1,555.13 crore were yet to be completed.

The development assumes significance as it has been almost two years since the award of the major infrastructure development project contract but the complete land has not yet been made available for the construction of the highway so far.

PROJECT REPORT

Total cost: Rs 2,461.64 cr

Total length: 75.543-km

Lanes: 6 ROW: 60m

  • Current status: 17% work done on Package-1, land acquisition pending
  • Total land requirement: 536.9 hectares
  • Deadline: Package 1: September 2025
  • Owner: NHAI
  • Model: HAM

Rajya Sabha MP from Ludhiana Sanjeev Arora told The Tribune on Wednesday that the work to construct the 30.3-km-long first package of the Greenfield highway project at the cost of Rs 906.51 crore has been progressing fast and has already achieved over 17 per cent completion till date.

The ruling Aam Aadmi Party (AAP) member in the Upper House of Parliament from Punjab, who reviewed the progress of the project, here recently, said the work on the second package comprising a 45.243-km-long highway at the cost of Rs 1,555.13 crore would also begin shortly as the land acquisition proceedings for the same had also been taken up on a priority basis.

NHAI officials briefed Arora that physical possession of 55.04 hectares, which accounted for 25.79 per cent, of the total 213.38 hectares of land required for the first phase of the project, was still awaited.

They said the deposit and payment of compensation for 53.18 hectares, determination of compensation for 1.83 hectares and final notification under Section 3D of the National Highways Act, 1956, was yet to be issued for 0.03 hectares of land required for Package-1.

The Rajya Sabha MP was also apprised that the land acquisition proceedings for 323.52 hectares to build a 45.243-km highway under the second phase of the project, were still pending at different stages.

The first component of the NH-754-AD would comprise 30.3 km while the second part would run into a 45.243-km stretch.

A total of 323.52 hectares of land was required to build the 45.243-km stretch of the highway in the jurisdiction of Ludhiana district, for which the total award amount of Rs 544.36 crore had been deposited and disbursed to landowners. However, the farmers were resisting the physical possession of the acquired land, seeking more money.

Much-delayed project

The construction work on the first package of the project was scheduled to begin by August 31 and was targeted to be completed by August 31, 2025, while the second component’s construction work was scheduled to take off by June 30 to be finished by June 30, 2025. But the non-availability of land has been delaying the start of the construction work for the second phase while that for the first phase, it has finally begun recently.

The 45.24-km stretch in Ludhiana district entails the civil cost of Rs 981 crore and land acquisition expenditure of Rs 544.36 crore, taking the total capital cost to Rs 1,555.13 crore.

While the Package-1 of the 30.3-km-long Greenfield expressway to build six-lane access controlled highway will start from junction with Amritsar-Bathinda Greenfield road (NH-754A) near Rampura Phul to junction with Moga-Barnala road (NH-703) near Tallewal village on the NH-754-AD falling in Bathinda, Moga and Barnala districts, the Package 2 comprising 45.24-km stretch will take off from junction with Moga-Barnala road (NH-703) near Tallewal village to junction with Delhi-Katra expressway (NE-5) near Ballowal village in Ludhiana on NH-754-AD.

The six-lane access-controlled highway will connect Ballowal village on the Delhi-Amritsar expressway with Rampura Phul on the Amritsar-Bathinda expressway.

Once constructed, the drive from Ludhiana to Bathinda will become smoother and faster as the project entails six-laning of the 75.543-km-long national highway 754-AD at the cost of Rs 2,461.64 crore.

The part of Ludhiana-Ajmer economic corridor (EC-8) was scheduled to be completed within 24 months under the Bharatmala Pariyojana Phase 1.

The widening and strengthening of the highway had been taken up by the NHAI in two parts under the hybrid annuity model (HAM) mode.

The total civil cost of the project has been estimated at Rs 2,461.64 crore, including Rs 658 crore for first part and Rs 981 crore for the second component, while Rs 754.71 crore was earmarked for the land acquisition, which included Rs 248.51 crore for Package-1 and Rs 574.13 crore for Package-2.

The total capital cost of the expressway was estimated at Rs 2,461.64 crore, including Rs 906.51 crore for the first component and Rs 1,555.13 crore for the second part.

The new Ludhiana-Bathinda expressway will pass through 36 villages falling in three districts of Ludhiana under Ludhiana and Raikot tehsils, Barnala under Barnala and Tapa tehsils, and Rampura Phul tehsil in Bathinda district.

About The Author

The Tribune News Service brings you the latest news, analysis and insights from the region, India and around the world. Follow the Tribune News Service for a wide-ranging coverage of events as they unfold, with perspective and clarity.


Top News

ED can’t arrest accused after special court has taken cognisance of complaint: Supreme Court

ED can’t arrest PMLA accused without court’s nod after filing of complaint, rules Supreme Court

The verdict comes on a petition filed by one Tarsem Lal chal...

Heatwave alert for northwest India; mercury may hit 45 degrees Celsius in Delhi

Heatwave alert for northwest India; mercury may hit 45 degrees Celsius in Delhi

A fresh heatwave spell will also commence over east and cent...


Cities

View All