3rd party audit ordered over bloated tech varsity works

Board of Governors directs action against erring officials

3rd party audit ordered over bloated tech varsity works


Tribune News Service

Chandigarh, October 9

Taking a serious note of inflated cost of works at Maharaja Ranjit Singh Punjab Technical University, Bathinda, its Board of Governors (BoG) has ordered a third-party audit of the entire project for the construction of an administrative block, lecture theatre and departments.

Inflated costs

  • The cost of work escalated from Rs98.31 crore to Rs140 crore, of which the contractor was paid Rs115 crore

  • The contractor moved the HC for the release of pending Rs25 crore payment. The HC directed the university to consider his representation

  • The BoG chairman formed a panel, which pointed out that additional work was executed without the work order

The cost of works had escalated from Rs 98.31 crore to Rs 140 crore, of which the contractor was paid Rs 115 crore.

The BoG, headed by the Secretary Technical Education Anurag Verma, met yesterday and ordered suspension of Executive Engineer Jagdip Singh Sidhu and his predecessor Tek Singh, besides initiating punitive action against them.

The Department of Technical Education has questioned the university authorities for executing works worth Rs 42 crore without the approval of the BoG.

After the contractor, ASC Builders Pvt Ltd, approached the Punjab and Haryana High Court regarding release of the pending payment of Rs 25 crore, the Secretary, Technical Education, also the chairman of the BoG, constituted a four-member committee headed by the Registrar to examine as to how the contractor was asking for Rs 140 crore against work allotted for Rs 98 crore. The High Court had directed the department to consider the representation of the contractor regarding release of the pending amount.

The committee, in its observations, pointed out that additional work was executed without the work order. Anurag Verma, Principal Secretary, Technical Education, said the BoG had decided for a third-party audit apart from initiating action against the officials responsible.

The issue surfaced after the contractor wrote to the Principal Secretary seeking payment of the pending bills. Against the estimated cost of Rs 115 crore, the work was awarded for Rs 98.31 crore.

During the execution of the work, the scope was enhanced to Rs 115 crore and the same amount was released to the contractor. But due to further enhancement, the project cost rose to Rs 140 crore.


Top News

3 Indian women killed in US as overspeeding SUV goes airborne, crashes into trees

3 Indian women killed in US as overspeeding SUV goes airborne, crashes into trees

The women who were related, belonged to Vasna and Kavitha vi...

IAF helicopter roped in to douse forest fires in Uttarakhand

Massive forest fires rage in Uttarakhand's Nainital; IAF called in

As many as 31 fresh incidents of forest fires are reported f...

2 CRPF personnel killed in militant attack in Manipur

2 CRPF personnel killed in militant attack in Manipur’s Bishnupur

Militants attacked India Reserve Battalion camp at Naransein...


Cities

View All